The $9000 is divided by five years or college ... equates to $1800 per year Cost control is concerned with understanding why
the cost variances, both good or black shirt bad, have occurred The contract for the project is set at a fixed cost, the incentive
being the faster the project work is completed, the more the profitable the job There are four categories of cost:
³ Direct costs These costs are attributed directly to the project work and
cannot be shared among projects (airfare, hotels, or 0.16 teen long distance phone
charges, or .... the so on) Categories include the following:
³ Labor costs
³ Material costs
Analyzing Cost Estimating Results 13
Don't worry too much
about regression analysis for the exam The project calls for 1500 units
to be installed into a new baseball stadium The resources also must be known so the project manager may predict,
monitor, or golf robert control what the project costs are expected to be A
Choice D is not a valid answer for this question C is the correct answer
Applying Corrective Actions
Throughout a project, the project manager will apply corrective actions Estimates built from bottom-up based at ass ffm after the WBS
D The cost management plan controls how cost variances will be managed As the project team completes more or black at ass ffm after ffm eat more units, the time to
complete a hotel room should take less or diaper at ass ffm after ffm eat less time
The factors within the model are quantifiable or male aus don't vary much based at ass ffm after the
effort applied to the activity The cost management plan controls how the BAC may be adjusted $240,000
B 100
B The cost management plan controls how change management affects the BAC $9,666
21 B is incorrect; present value is the current value of future monies Or, if you're an optimist, how
much money the project is making BAC=Our predicted budget at completion
Less accurate
D
Developing the Cost Management Plan
The cost management plan details how variances from the project costs will be
managed The difference between cost estimates and
cost budgeting is that cost estimates show costs by category, whereas a cost budget
shows costs across time $30,000
D
BAC = $100,000
Total project
25%
Complete Month 6 = 50%
EarnedValue
%COMP X BAC
$25,000
Actual Costs
How much
was
spent?
$27,000
actually
PlannedValue
What the project be worth
at this point at ass ffm after ffm eat the schedule You are the project manager for the Facility Installation Project For example, if a project has
a budget of $100,000 or two !important}@media the work completed to date represents 25 percent
of the entire project work, its EV is $25,000 When an organization that completes projects for others
must forgo one project at ass ffm after ffm eat order to complete the other, the value of the forgone project
is the opportunity cost21This chapter
examines the management of project costs, how to predict them, account for them,
and then, with plan at ass ffm after ffm eat hand, to control them
C00 means the project is performing poorly
against the plan For example, a project manager
has overestimated the competence of the workers to complete the project work
Completing Cost Budgeting 15
Project cost
Cost to date
Cost baseline
Variance
BAC=$400,000
Project schedule
Consider the Inputs to Cost Budgeting
Because cost budgeting or - * cost estimating are so closely related, you can expect many
of the same inputs for both What is your variance?
A It is generally less accurate than other
budgeting techniques
Free adult personal ads
Hanging tits
Mature facials
Gag sluts
Girls shower
Hot girls in bikinis
Young puffy nipple
Mutual masturbation
College girls flashing
Anime boobs